Full replacement of Section 4B would require a 14-day production shutdown at an estimated cost of USD 4.2M against a residual exposure assessed at USD 310k. Inspection frequency has been increased to quarterly UT scanning, cathodic protection has been upgraded and a pressure de-rate applied. Further reduction is grossly disproportionate to the benefit gained.
Why is this risk as low as reasonably practicable?
✓
Residual riskReviewed
Treated (residual) risk scoreRead-only
7
Residual levelMajor
✓
Evidence2 files
Click here to upload filesMinimum one file, assessment docs, study extracts, inspection reports